Monitoring
and Evaluation
Quality Assurance
Quality management is a
mechanism of ensuring that projects are executed to the highest
standards specified within given time and resources. This is
achieved through frequent technical and financial audits of
projects, employing both deskwork and physical inspection.
Monitoring and Evaluation
The Monitoring and Evaluation
Section was
established as part of the National Road Fund Agency (NRFA) in
2002 with the objectives of providing NRFA with some technical
capacity to review technical documentation, undertake technical
audit and evaluation of projects being funded from both the road
fund and some donor funds/loans. This became even more necessary
with added responsibility of coordinating the ROADSIP.
Originally, the Engineering
Section was set up and consisted of two sections and managed by
two engineers, one in Highway Engineering Section (planning
section) and one in Inspectorate Section (monitoring section).
In fulfillment of the desire by
the Committee of Ministers on RMI (Road Management Initiative) and
Cooperating Partners that the National Roads Board is strengthened
to adequately execute its functions as outlined in the Road Fund
Act No. 13 of 2002 and the added role of coordinating of
ROADSIP, the Monitoring and Evaluation Section strives to achieve its
objectives.
Like in the
previous year (2006), the Monitoring and Evaluation Department
continued performing the following functions:
a)
reviewing
technical documentation submitted by implementing agencies
(mainly the Road Development Agency – RDA);
b)
carrying
out technical audit of road projects (mainly out-sourced );
c)
monitoring
project procurement (mainly foreign financed) and;
d)
monitoring
project implementation through physical inspection as well as
desk study.
The
Department reviewed technical reports such as consultancy reports
and tender evaluation reports, draft annual work plan for 2008,
project payment certificates, terms of reference for both locally
financed as well as foreign financed consultancies etc.
Technical
audit tasks were all outsourced due to limited number of technical
staff in the Department who, most of the time, were required to
process huge volume of payment certificates on daily basis as well
as undertake random site inspection and perform other urgent tasks
assigned to the Department.
In
monitoring project procurement, emphasis was placed more on
foreign financed projects for which NRFA had a role of
coordinating activities of implementing agencies and reporting to
cooperating partners (foreign financiers). For locally financed
road projects or activities, the implementing agencies (RDA and
RTSA) had delegated responsibility to adjudicate tenders up to
specified thresholds by the Zambia National Tender Board through
respective tender committees in the two agencies. Tenders above
the specified thresholds were always referred to the Zambia
National Tender Board to adjudicate.
IMPLEMENTATION
MONITORING AND EVALUATION
Monitoring
of programme implementation and evaluation was, like for pervious
years, achieved through physical inspection of projects as well as
contract progress tracking through desk review.
In 2007
around 33 road projects (new construction, upgrading and periodic
maintenance) worth K524.5 billion covering 2,400 Km billion were
inspected.
In addition
to physical inspection the section checked to verify validity,
authenticity and correctness of 2,020 payment certificates from
the contracts that were active during the year and well over K3.0
billion claimed erroneously on various certificates was detected
and saved.
One
contract was recommended for termination on account of non
performance and poor workmanship on rehabilitation of selected
township roads in
Kitwe
.
2007 Plan Vs 2006 Plan
|
Year
|
Cost
(US$ m)
|
Projects
|
KM
to be done
|
Intervention
|
|
2006
|
135.173
|
Various
|
16,909.935
|
Routine, periodic,
Rehabilitation, emergency and supervision
|
|
2007
|
256.095
|
26,340.240
|
Compared to
2006 as shown in Table 15 above, the road maintenance programme in
both activity and cost was much higher in 2007 primarily due to
continuation of all performance maintenance contracts whose
duration ranged from 3 to 4 years but renewable every year
depending on good performance. In addition, more new projects were
programmed to start during the year.
Table 16:
Progress in 2007 Vs Progress in 2006
|
Agency
|
Year
|
Cost
(US$ m)
|
No
of Projects
|
Km
Done
|
Intervention
|
|
RDA
|
2006
|
60.695
|
368
|
13,764
|
Routine, periodic,
Rehabilitation, upgrading, emergency and supervision
|
|
2007
|
113.124
|
391
|
19,906
|
Exchange
rate is US$1 equivalent to ZMK 3,800.
Like the
previous year, late procurement of new contracts for routine
maintenance on Trunk,
Main
and District Roads including periodic maintenance on the same
classes of roads contributed to the low overall performance
compared to the programme. However, more road maintenance was done
in 2007 compared to 2006 particularly on routine maintenance.
Even though
a lot of labour-intensive routine maintenance was undertaken
during the year, the amount jobs created could not be determined
because labour statistics and returns were not submitted.
The
condition of the paved road network, based on measuring criteria
employed previously (other than the international roughness index,
IRI) improved marginally from 65% Good, 15% Fair and 20% poor in
December 2006 to 65% Good, 20% Fair and 15% Poor in December 2007
primarily due to the few periodic maintenance contracts initiated
covering Great East Road (Mutenguleni to Mwami Border Post),
Solwezi – Mwinilunga, Ndola – Mufulira, Sabina – Mufulira,
Kaoma – Mongu and Mufulira – Mokambo Roads.
The
little progress achieved on these contracts (even mere preparatory
works like patching potholes in readiness for resealing) changed
the conditions of these roads from being poor to fair. Hence the
overall increase in paved road network in Fair condition by 5%.
Roads in Good condition have not changed from 2006 level despite
having had a few rehabilitation projects running during the year,
this could be attributed to deterioration of some roads that were
in fair condition at the beginning the year by the same length as
the rehabilitation done during the year, hence, offsetting
achievements made in rehabilitation
|