Project Name

 

Progress Contract Amount Summary
GRZ Fund
Chitongo-Namwala Road Project, Supervision Completed K0.816 billion This project is complete and was funded by GRZ.
Chitongo-Namwala Civil Works Completed K12.361 billion This project was completed also funded by GRZ.
Choma-Chitongo Civil Works Yet to Start K17.878 billion
Luanshya-Mpongwe Supervision Completed K4.110 bilion
Luanshya-Mpongwe Civil Completed K18.081 billion
Mutanda-Kasempa Supervision Completed K6.500 billion
Mutanda-Kasempa Civil Works Completed K101.154 billion
Isoka-Muyombe Completed K19.086 billion
Kasama-Luwingu On-going K122.564 billion
Kashikishi-Lunchinda 25% K149.315 billion A direct GRZ counterpart funded project and works are ongoing.
Kalungwishi Bridge Completed K9.230 billion Project Complete
Chirundu Bridge Completed K4 billion Project is complete
Chipata-Lundazi 15% US$4.63 million A GRZ funded project whose works are at 15% at present.
Road Fund
Turnkey Projects in 7 Provincial Capitals funded by Road Fund Completed K3.6 billion This is an intervention Turnkey project by National Roads Board to design and rehabilitate urban roads in 7 provincial capitals under Road Fund. Priority urban roads were improved in Livingstone, Mongu, Chipata, Kabwe, Kasama, Solwezi and Mansa
Turnkey Project in 5 Mining Towns - Road Fund Completed K4.3 billion Another intervention by National Roads Board which involved rehabilitation of urban roads in 5 mining towns on the copperbelt: Kalulushi, Luanshya, Chingola, Chililabombwe and Mufulira under the Turnkey Project funded by Road Fund. Now Complete
Kasama-Mpika Road Project- Completed K12.8 billion A road rehabilitation project funded by Road Fund under National Roads Board. The project is complete.
Chingola-Solwezi Road Project Completed K10.9 billion A Road Fund project under National Roads Board which is now 100% complete.
Chingola-Kasumbalesa Road Project 60% Completed K5.2 billion
Road Line Marking Complete K2.3 billion A Road Fund project under National Roads board is complete.
Vegetation Control 90% Completed K1.3 billion
Feeder Road Maintenance Ongoing K32.46 billion 104 Contracts under Ministry of Local Government and Housing being commissioned and works are ongoing. 3064Km roads works is going on
Urban Roads Maintenance Ongoing K21.42 billion 28 contracts were commissioned by Ministry of Local Government and Housing funded by Road Fund and works are ongoing.
Performance Contracts Ongoing K15.40 billion performance contracts of 15,000km countrywide are ongoing and works funded by Road Fund.
Magoye-Chivuna Completed US$0.23 million Road fund project which has since been completed.
Accelerated urban roads rehabilitation in Livingstone, Choma, Mazabuka, Lusaka and Kabwe Completed K35,332,349,909.97 Accelerated Urban Road Rehabilitation project implemented by Ministry of Local Government and Housing and have since been completed.
Rehabilitation of selected roads in Mufulira and Ndola K11,232,000,000 Rehabilitation of selected road in Mufulira and Ndola implemented by Ministry of Local Government and Housing
Rehabilitation of selected township roads in Kitwe K11,600,000,000 Rehabilitation of selected township roads in Kitwe implemented by Ministry of Local Government and Housing
Donor Fund
Phase II Lusaka City Roads - JICA Completed US$30 million Lusaka Phase II Stage II city roads rehabilitation project funded by Japanese government through JICA is now complete. The contractor SHIMZU Corporation carried out rehabilitation works on Great East road (14km), Great North road (4.3km) and Machinchi road (2.3km).
Kapiri-Chisamba Roads EU funded Completed US$12 million The EU funded road project is now complete. Rehabilitation of this road has enhanced improvement trade relations both internally and internationally by ensuring that the road is in good condition.
JICA - Chirundu Bridge 100% Complete US$25 million The Japanese government through JICA provided funding for the construction of Chirundu bridge. The contract was signed in November 2000 with Contractor Kajima Corporation. This project was completed in 2002. This bridge was commissioned by the President of the Republic of Zambia on 11 December 2002. The construction of this new bridge has facilitated improvement of trade relations between Zambia and her neighbouring countires by easing congestion at the Chirundu Border Post.
Monze-Zimba Road, EU Funded Project 100% Completed US$21 million The rehabilitation of the road is being funded by the European Union and covers a stretch of about 210km. The project commenced in Febraury 2000 and works completed in September 2002. The key trunk road is now in good condition and will result in improved internal and international trade.
Mongu-Kalabo Road 60% US$37 million Upgrading of 70km of Mongu-Kalabo Road is funded by BADEA/Kuwait/OPEC Fund and work is progressing well. The contract was signed in July 2002 and work is still going on although it was envisaged that works would be complete by February 2004.
Livingstone-Sesheke Road Completed US$23 million The project consisted of construction of of 210km of road funded by KfW Germany. The project is complete
Katimamulilo Bridge Construction completed US$8 million A KfW Germany funded project. The project was completed and the bridge was commissioned in May 2004.
Periodic Maintenance of Roads - World Bank Funded 95% Complete US$70 million Periodic maintenance of M15 Siavonga Road Turn off to Kariba Dam Gate (48.5km) was funded by World Bank under IDA credit and is 95% complete now.
Community Roads/Capacity Building /IMT/Engineering Design/ROADSIP Phase II PPF 98% Complete US$70 million Project funded by World Bank under IDA Credit. This includes design study of Lot 1 - Livingstone-Zimba, Kafue-Chirundu and design study of Lot 2 - Ndola-Mufulira-Mwambashi-Mokambo & Kafulafuta-Luanshya.
Capacity Building and Institutional Development - NORAD Completed US$4 million Project for capacity building and Institutional development to Roads Department funded by NORAD was completed.
Lusaka City Roads Phase I Completed K18.400 billion Funded by World Bank and the project is complete
Lusaka-Mongu 50% US$14million Donor funded project under DANIDA and works have since progressed at 50% now.
Lusaka-Kabwe Substantially Complete US$0.78 million IDA funded project and is substantially complete
Lusaka-Makeni Substantially Complete US$0.36 million IDA counterpart funded project which is substantially complete.
Mporokoso-Bulaya Complete US$0.42 million A direct GRZ counterpart funded project which is complete.
Lusaka-Mumbwa 36% US$0.23 million A direct GRZ counterpart funded project whose works are at 36%.
Lusaka City Roads Phase II Commissioned US$30 million Funded by JICA and the progress is complete
Axle Load Control On going US$4 million The project is ongoing

 